SJSSAA Kapar - Instrument recalibration for Unit 6
Boiler & Turbine
Saftech was awarded a sub-contracting work from
Instrutech Engineering to recalibrate
instrument for SJSSAA Power Station Phase III Unit 6 Overhaul Inspection. This
contract is the continuation of the contract that was awarded earlier for Unit
No. 5 warranty inspection. Works for Unit No. 6 have started from November 2002 and
schedule to be completed
around January 2003. Scope of works includes Pressure and Temperature
Transmitter, Switches and gauges. The area covered is for equipment installed in
Turbine contract, Boiler Contract and Ash Handling Plant Phase 3.