Saftech
was awarded a contract work from TNBG SJSSAA for the relocation of 11KV Supply
from District Sub Station to Phase III 11 KV Station Board-B for the 3.3KV Coal
Handling Plant. Works is expected to start around mid April 2003 and expects to
be completed by end of July 2003.
Latest Update : Saftech have complete the re-powering works
and successful hand-over of the plant to TNB Generation on the 28th July 2003.